22 WestEdge

Charleston, SC
Back
Owner
Gateway Development Services
General Contractor
Trident Construction
Schedule Duration
08/2018
to
11/2019
Architect / Engineer
Perkins + Will / Integral Group Engineering
Mechanical Subcontract Value
$
4.6
M
Awards

Project Overview

Bell provided Mechanical and Plumbing subcontracting services for this 160,214 Gross SF, eight-story office building.

The all-glass building is the tallest office building in the Charleston skyline at 125 feet and Charleston’s only modern Class-A Office tower.

The first floor consists of 15,750 SF of retail space. The upper seven floors encompass 138,500 RSF of Class-A office. Top floor will accommodate lab and clean room space. The 7th floor contains The Harbour Club, a full-service dining, event, and meeting facility with a roof-top terrace. Office floors will be served by VAV, water cooled, self-contained DX air handling units.

Major Mechanical Equipment includes:

  • Seven (7) 15,000+/- cfm Water-Cooled Self-Contained AHUs
  • One (1) Water to Water Heat Exchanger
  • One (1) 430 Ton Cooling Tower
  • One (1) 15,500 cfm Dedicated Outdoor Air Unit